Q. Which of the following is the task ofproject indicators: (Solved)

1. help in assessment of status of ongoing project

2. track potential risk

3. help in assessment of status of ongoing project and track potential risk

4. none of the above

  • c. help in assessment of status of ongoing project and track potential risk