Q. The purpose of earned value analysis is to (Solved)

1. determine how to compensate developers based on their productivity

2. provide a quantitative means of assessing software project progress

3. provide a qualitative means of assessing software project progress

4. set the price point for a software product based on development effort

  • b. provide a quantitative means of assessing software project progress