Q. Which one of the following statements is NOT correct? (Solved)

1. LFT is calculated from the LFT of the head event.

2. Slack can be calculated by adding EFT and LFT of any job.

3. EFT is the sum of the EST and the time of duration for any event.

4. The Total Project time is the shortest possible time required in completing the project.

  • b. Slack can be calculated by adding EFT and LFT of any job.