Q. The time by which an activity can be rescheduled without affecting the otheractivities - preceding or succeeding is called as (Solved)
1. Slack
2. Independent Float
3. Free Float
4. Total Float
- b. Independent Float
1. Slack
2. Independent Float
3. Free Float
4. Total Float