Q. ----------- in Activity Based Costing is like ‘cost centre’ in traditional costing. (Solved)
1. Activity Cost Driver
2. Cost object
3. Cost pool
4. Resource Cost driver.
- c. Cost pool
1. Activity Cost Driver
2. Cost object
3. Cost pool
4. Resource Cost driver.