Q. In which of the following stages practicability of project is ensured? (Solved)
1. Planning stage
2. Briefing stage
3. Construction stage
4. None of the above
- b. Briefing stage
1. Planning stage
2. Briefing stage
3. Construction stage
4. None of the above