Q. In CPM analysis, (Solved)
1. Emphasis is given to activities
2. Uncertainties are not allowed
3. Activities are represented by arrows
4. All the above
- d. All the above
1. Emphasis is given to activities
2. Uncertainties are not allowed
3. Activities are represented by arrows
4. All the above