Q. Select the incorrect statement. (Solved)

1. A critical path always begins at the very first event.

2. A critical path always terminates at the last event.

3. Critical activities control the project duration.

4. Critical activity is the one for which free float is zero.

  • d. Critical activity is the one for which free float is zero.