Q. Select the incorrect statement. (Solved)
1. A critical path always begins at the very first event.
2. A critical path always terminates at the last event.
3. Critical activities control the project duration.
4. Critical activity is the one for which free float is zero.
- d. Critical activity is the one for which free float is zero.