Q. In the given figure, the network of a project represents (Solved)
1. Activity of an excavation of a footing
2. Activity of an excavation which starts at event No. 1 and ends at even No.2
3. Activity of excavation which takes 8 units of time
4. None of these
- c. Activity of excavation which takes 8 units of time