Q. Pick up the incorrect statement from the following: (Solved)

1. The activity is the time consuming part of a project

2. The beginning and end of a job, are called events

3. The activity which consumes maximum time, is called a node

4. Logically and sequentially connected activities and events form a network

  • c. The activity which consumes maximum time, is called a node