Q. Pick up the incorrect statement from the following: (Solved)
1. The activity is the time consuming part of a project
2. The beginning and end of a job, are called events
3. The activity which consumes maximum time, is called a node
4. Logically and sequentially connected activities and events form a network
- c. The activity which consumes maximum time, is called a node