Q. Under normal conditions using an ordinary cement, the period of removal of the form work, is: (Solved)
1. 7 days for beam soffits
2. 14 days for bottom slabs of spans 4.6 m and more
3. 21 days for bottom beams over 6 m spans
4. all the above
- d. all the above