Q. Under normal conditions using an ordinary cement, the period of removal of the form work, is: (Solved)

1. 7 days for beam soffits

2. 14 days for bottom slabs of spans 4.6 m and more

3. 21 days for bottom beams over 6 m spans

4. all the above

  • d. all the above