Q. Which of the following is a correct formula for computing direct materials price variance? (Solved)
1. Standard quantity purchased × (Actual rate - Standard rate)
2. Actual quantity purchased × (Actual rate - Standard rate)
3. Standa
4. quantity purchased × (Actual rate + Standard rate)
- b. Actual quantity purchased × (Actual rate - Standard rate)