Q. Choose the wrong statement in respect of value engineering. (Solved)

1. Value engineering is applied to products which will be produced in future.

2. Value analysis is applied to products already in production

3. Supply and demand conditions

4. Cost is calculated item wise

5. Value engineering deals with improoving quality/performance to satisfy customer.

  • d. Cost is calculated item wise
Subscribe Now

Get All Updates & News