Q. If D = duration, EF = earliest finish time, ES = earliest start time, LF = latest finish time, LS = latest start time, which relationship does not hold? (Solved)
1. EF = D - ES
2. EF = D + ES
3. LF = LS + D
4. None of the above
5. Supply and demand conditions
- a. EF = D - ES