Q. Choose the correct statement. (Solved)
1. CPM and PERT are event oriented techniques
2. CPM and PERT are activity oriented techniques
3. CPM is an activity oriented technique while PERT is an event oriented technique
4. None of the above
5. Supply and demand conditions
- c. CPM is an activity oriented technique while PERT is an event oriented technique