Q. In the matter of liquidated damages (Solved)
1. The plaintiff is entitled to recover the agreed amount to compensation for the loss suffered
2. The plaintiff is not entitled to recover the agreed amount of compensation for the loss suffered
3. The plaintiff is entitled to recover the agreed amount of compensation without having to prove the exact loss suffered
4. The plaintiff is entitled to recover the agreed amount of compensation and has to prove the exact loss suffered
- c. The plaintiff is entitled to recover the agreed amount of compensation without having to prove the exact loss suffered