Q. If standard hours are 400 @ Rs. 1 per hour and actual hours are 380 @ Rs. 1.25 perhour, the labour rate variance is: (Solved)
1. Rs. 20 (Favourable)
2. Rs. 25 (Favourable)
3. Rs. 100 (Adverse)
4. Rs. 95 (Adverse)
- d. Rs. 95 (Adverse)