Q. Pick up the correct reason for making conceptual (or preliminary) estimate from thefollowing: (Solved)
1. To have a check on a definitive cost estimate
2. To check quotations from contractors and/or sub-contractors
3. To compute target estimate for the owner while drawing and specifications are in initial stage
4. All of these
- d. All of these